Quarterly Schedules

HRERA Panchkula
Project Registration Number : HRERA-PKL-KNL-81-2018
Project Name : YET TO BE DECIDED
Project Number : RERA-PKL-360-2018
Project Type : NEW
Report Online Submission Date : 09-Oct-2019
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)2904.34
2Estimated cost of construction of apartments0.00
3Estimated cost of infrastructure & other structure4339.28
4Other cost including EDC taxes, levies, etc215.99
Total7459.61



Name of the approvalStatusDate
Layout PlanObtained Approval on25-06-2021
Demarcation PlanObtained Approval on30-05-2018
Zoning PlanObtained Approval on07-09-2021
Service PlansObtained Approval on24-08-2018
Electricity PlansHave not applied till dateN/A
Total Expenditure on the project3615.11
Expenditure made upto the date of Registration212.56



EDC due as on the date of Registration118.06

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0.00
2Amount collected from allottees against booked plots and/or apartments0.00
3Amount availed from the bank/financial institutions0.00
4Amount contributed by the promoters/his associates425.01
5Any other receipt0.00
Total425.01



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0.00
2Expenditure on infrastructure & other structure306.96
3Other costs including EDC, taxes, etc118.06
Total425.02
Balance3190.10



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account0.00
3Amount withdrawn during the quarter0.00
4Balance at the end of the quarter0.00
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0.00
2Apartments0.00
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0.00
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 05-10-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 05-10-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 05-10-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 07-10-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 07-10-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance425.02
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0.35
5Any other receipt0
Total425.37



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0.35
3Other costs including EDC, taxes, etc0
Total0.35
Balance3189.74



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1NIL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-10-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-10-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-10-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-10-2019  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-10-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance425.37
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0.18
5Any other receipt0
Total425.55



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0.18
3Other costs including EDC, taxes, etc0
Total0.18
Balance3189.56



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates31.39
5Any other receipt0
Total31.39



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure31.39
3Other costs including EDC, taxes, etc0
Total31.39
Balance3158.17



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 10-01-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 10-01-2020  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 10-01-2020  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 10-01-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 10-01-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3158.17
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates85.69
5Any other receipt0
Total3243.86



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure85.69
3Other costs including EDC, taxes, etc0
Total85.69
Balance3072.48



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 08-10-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 08-10-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 08-10-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 08-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 08-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3072.48
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3072.48



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc0
Total0
Balance3072.48



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 08-10-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 08-10-2020  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 08-10-2020  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 08-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 08-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3072.48
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates1.84
5Any other receipt0
Total3074.32



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure1.84
3Other costs including EDC, taxes, etc0
Total1.84
Balance3070.65



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2020  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3070.65
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3070.65



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc0
Total544.46
Balance3070.65



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-01-2021  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-01-2021  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-01-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-01-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-01-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3070.65
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates5.25
5Any other receipt0
Total3075.90



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure5.25
3Other costs including EDC, taxes, etc0
Total549.71
Balance3065.4



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date118.06
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-04-2021  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-04-2021  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-04-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-04-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-04-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3075.90
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates18.09
5Any other receipt0
Total3093.99



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure1.61
3Other costs including EDC, taxes, etc16.48
Total567.80
Balance3047.31



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony207
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A0



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc134.54
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date134.54
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-07-2021  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-07-2021  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-07-2021  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-07-2021  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-07-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3047.31
2Amount collected from allottees against booked plots and/or apartments1580.99
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates2955.88
5Any other receipt0
Total7584.18



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure2874.43
3Other costs including EDC, taxes, etc81.45
Total3523.68
Balance3935.93



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account1580.99
3Amount withdrawn during the quarter1564.14
4Balance at the end of the quarter16.85
Total Plots in the colony248
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A73



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc215.99
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 12-10-2021  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 12-10-2021  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 12-10-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 12-10-2021  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 12-10-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3935.93
2Amount collected from allottees against booked plots and/or apartments218.31
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates31.99
5Any other receipt0
Total4186.23



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure31.99
3Other costs including EDC, taxes, etc0
Total3555.67
Balance3903.94



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter16.85
2Amount deposited in Escrow Account218.31
3Amount withdrawn during the quarter235.16
4Balance at the end of the quarter0
Total Plots in the colony248
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A34



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.5



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 13-01-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 13-01-2022  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 13-01-2022  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 13-01-2022  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 13-01-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3903.94
2Amount collected from allottees against booked plots and/or apartments199.71
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4103.65



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0.23
3Other costs including EDC, taxes, etc0
Total3555.90
Balance3903.71



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account199.71
3Amount withdrawn during the quarter199.71
4Balance at the end of the quarter0
Total Plots in the colony248
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-04-2022  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-04-2022  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-04-2022  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-04-2022  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-04-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3903.71
2Amount collected from allottees against booked plots and/or apartments480.70
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4384.41



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure237.57
3Other costs including EDC, taxes, etc0
Total3793.47
Balance3666.14



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account480.70
3Amount withdrawn during the quarter480.70
4Balance at the end of the quarter0
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1DSS9



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2022  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2022  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2022  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3666.14
2Amount collected from allottees against booked plots and/or apartments372.19
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4038.34



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure13.13
3Other costs including EDC, taxes, etc0
Total3806.59
Balance3653.02



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account372.19
3Amount withdrawn during the quarter367.34
4Balance at the end of the quarter4.85
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT24
2DSS6



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1-0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1-0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2022  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2022  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2022  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3653.02
2Amount collected from allottees against booked plots and/or apartments1147.40
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4800.42



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure137.57
3Other costs including EDC, taxes, etc0
Total3944.16
Balance3515.45



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter4.85
2Amount deposited in Escrow Account1147.40
3Amount withdrawn during the quarter1126.25
4Balance at the end of the quarter26.01
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT71
2DSS2



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1-0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1-0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-01-2023  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-01-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-01-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-01-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-01-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3515.45
2Amount collected from allottees against booked plots and/or apartments1324.70
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4840.15



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure233.35
3Other costs including EDC, taxes, etc0
Total4177.51
Balance3282.10



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter26.01
2Amount deposited in Escrow Account1324.70
3Amount withdrawn during the quarter1340.71
4Balance at the end of the quarter10.00
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT7



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1-0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1-0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-04-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-04-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-04-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3282.10
2Amount collected from allottees against booked plots and/or apartments364.95
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3647.04



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure153.51
3Other costs including EDC, taxes, etc0
Total4331.02
Balance3128.59



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter10.00
2Amount deposited in Escrow Account364.95
3Amount withdrawn during the quarter372.43
4Balance at the end of the quarter2.52
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT15
2DSS1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2023  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3128.59
2Amount collected from allottees against booked plots and/or apartments229.37
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3357.96



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure24.81
3Other costs including EDC, taxes, etc0
Total4355.83
Balance3103.78



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter2.52
2Amount deposited in Escrow Account229.37
3Amount withdrawn during the quarter231.90
4Balance at the end of the quarter0
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT5



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2023  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3103.78
2Amount collected from allottees against booked plots and/or apartments58.26
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3162.04



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure37.91
3Other costs including EDC, taxes, etc0
Total4393.74
Balance3065.87



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account58.26
3Amount withdrawn during the quarter58.26
4Balance at the end of the quarter0
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-01-2024  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-01-2024  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-01-2024  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-01-2024  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-01-2024  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3065.87
2Amount collected from allottees against booked plots and/or apartments103.97
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3169.84



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure4.44
3Other costs including EDC, taxes, etc0
Total4398.18
Balance3061.43



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account103.97
3Amount withdrawn during the quarter75.45
4Balance at the end of the quarter28.52
Total Plots in the colony266
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1PLOT2



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc118.06
4Others Expenditure94.50



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date215.99
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-04-2024  View 
2 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-04-2024  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-04-2024  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-04-2024  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-04-2024  View