Quarterly Schedules

HRERA Panchkula
Project Registration Number : HRERA-PKL-RTK-96-2019
Project Name : PALM DRIVE ROHTAK
Project Number : RERA-PKL-339-2018
Project Type : NEW
Report Online Submission Date : 18-Apr-2023
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)0
2Estimated cost of construction of apartments0
3Estimated cost of infrastructure & other structure681.76
4Other cost including EDC taxes, levies, etc127.75
Total809.51



Name of the approvalStatusDate
Layout PlanObtained Approval on19-06-2018
Demarcation PlanObtained Approval on11-09-2018
Zoning PlanObtained Approval on11-09-2018
Service PlansObtained Approval on09-01-2019
Electricity PlansHave not applied till dateN/A
Total Expenditure on the project681.76
Expenditure made upto the date of Registration17.225



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance24.49
2Amount collected from allottees against booked plots and/or apartments236.55
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total261.04



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure138.11
3Other costs including EDC, taxes, etc97.92
Total236.03
Balance25.01



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter24.49
2Amount deposited in Escrow Account163.21
3Amount withdrawn during the quarter162.68
4Balance at the end of the quarter25.01
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A13
2B1
3D3



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure138.11
2Apartments0
3EDC, IDC, etc0
4Others Expenditure24.57



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date127.75
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance25.01
2Amount collected from allottees against booked plots and/or apartments221.90
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total246.91



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure169.89
3Other costs including EDC, taxes, etc43.34
Total213.23
Balance33.68



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter25.01
2Amount deposited in Escrow Account179.49
3Amount withdrawn during the quarter170.73
4Balance at the end of the quarter33.68
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A3
2B1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure169.89
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0.84



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date127.75
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance33.68
2Amount collected from allottees against booked plots and/or apartments56.70855
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates34.27500
5Any other receipt79.28741
Total170.27096



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure72.49489
3Other costs including EDC, taxes, etc13.75
Total86.24489
Balance84.02607



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter33.68
2Amount deposited in Escrow Account65.83088
3Amount withdrawn during the quarter98.71732
4Balance at the end of the quarter0.79479
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
2 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance84.02607
2Amount collected from allottees against booked plots and/or apartments103.56701
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates164.27500
5Any other receipt0
Total351.86808



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure21.39258
3Other costs including EDC, taxes, etc49.10000
Total70.49258
Balance281.37550



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.79479
2Amount deposited in Escrow Account104.06701
3Amount withdrawn during the quarter86.36235
4Balance at the end of the quarter18.49945
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 3



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance281.37550
2Amount collected from allottees against booked plots and/or apartments34.26835
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates3.09065
5Any other receipt0
Total318.73450



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure10.64977
3Other costs including EDC, taxes, etc33.95866
Total44.60843
Balance274.12607



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter18.49945
2Amount deposited in Escrow Account56.30940
3Amount withdrawn during the quarter73.88883
4Balance at the end of the quarter0.98002
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 4



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
2 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance274.12607
2Amount collected from allottees against booked plots and/or apartments70.61215
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates56.00
5Any other receipt0
Total400.73822



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure81.37272
3Other costs including EDC, taxes, etc35.49230
Total116.86502
Balance283.87320



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.98002
2Amount deposited in Escrow Account93.17590
3Amount withdrawn during the quarter90.96934
4Balance at the end of the quarter3.18658
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 2



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance283.87320
2Amount collected from allottees against booked plots and/or apartments35.44983
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates21.90
5Any other receipt0
Total341.22303



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure5.19845
3Other costs including EDC, taxes, etc14.25610
Total19.45455
Balance321.76848



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter3.18658
2Amount deposited in Escrow Account84.91079
3Amount withdrawn during the quarter75.66023
4Balance at the end of the quarter12.43714
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 3



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance321.76848
2Amount collected from allottees against booked plots and/or apartments10.00911
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total331.77759



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure8.72348
3Other costs including EDC, taxes, etc8.27230
Total16.99578
Balance314.78181



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter12.43714
2Amount deposited in Escrow Account70.79653
3Amount withdrawn during the quarter83.11683
4Balance at the end of the quarter0.11684
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 5



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance314.78181
2Amount collected from allottees against booked plots and/or apartments12.76002
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates10.20
5Any other receipt0
Total337.74183



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc0.03997
Total0.03997
Balance337.70186



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.11684
2Amount deposited in Escrow Account28.22508
3Amount withdrawn during the quarter20.27766
4Balance at the end of the quarter8.06426
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 4



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance337.70186
2Amount collected from allottees against booked plots and/or apartments1.10
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates21.00
5Any other receipt0
Total359.80186



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure19.41668
3Other costs including EDC, taxes, etc5.00
Total24.41668
Balance335.38518



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter8.06426
2Amount deposited in Escrow Account7.10
3Amount withdrawn during the quarter14.74603
4Balance at the end of the quarter0.41823
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance335.38518
2Amount collected from allottees against booked plots and/or apartments32.54937
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates42.08
5Any other receipt0
Total410.01455



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure43.60540
3Other costs including EDC, taxes, etc20.25
Total63.85540
Balance346.15915



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.41823
2Amount deposited in Escrow Account84.31495
3Amount withdrawn during the quarter81.45506
4Balance at the end of the quarter3.27812
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance346.15915
2Amount collected from allottees against booked plots and/or apartments522.09388
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates6.0100
5Any other receipt0
Total874.26301



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure8.31736
3Other costs including EDC, taxes, etc133.78
Total142.09736
Balance732.16567



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter3.27812
2Amount deposited in Escrow Account588.19797
3Amount withdrawn during the quarter570.76007
4Balance at the end of the quarter20.71602
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 43



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance732.16567
2Amount collected from allottees against booked plots and/or apartments127.41230
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates201.44022
5Any other receipt0
Total1061.01819



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure16.29290
3Other costs including EDC, taxes, etc149.50
Total165.76290
Balance895.25529



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter20.71602
2Amount deposited in Escrow Account134.91348
3Amount withdrawn during the quarter155.37280
4Balance at the end of the quarter0.25670
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 6



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance895.25529
2Amount collected from allottees against booked plots and/or apartments125.49419
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates5.03890
5Any other receipt0
Total1025.78838



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure6.34895
3Other costs including EDC, taxes, etc236.50
Total242.84895
Balance782.93943



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.25670
2Amount deposited in Escrow Account137.27554
3Amount withdrawn during the quarter137.33065
4Balance at the end of the quarter0.20159
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 6



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance782.93943
2Amount collected from allottees against booked plots and/or apartments52.18009
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates45.49200
5Any other receipt0
Total880.61152



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure6.49983
3Other costs including EDC, taxes, etc105.25
Total111.74983
Balance768.86169



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.20159
2Amount deposited in Escrow Account54.55009
3Amount withdrawn during the quarter54.27806
4Balance at the end of the quarter0.47362
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 9



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 
2 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance40.65005
2Amount collected from allottees against booked plots and/or apartments22.75750
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates17.21250
5Any other receipt0
Total80.62005



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure14.13656
3Other costs including EDC, taxes, etc0
Total14.13656
Balance66.48349



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.74612
2Amount deposited in Escrow Account44.58250
3Amount withdrawn during the quarter28.64906
4Balance at the end of the quarter16.67956
Total Plots in the colony229
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL 9



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-04-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-04-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-04-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-04-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-04-2023  View