Quarterly Schedules

HRERA Gurugram
Project Registration Number : GGM/365/97/2019/59 DATED- 15.10.2019
Project Name : M3M 113 MARKET
Project Number : RERA-GRG-319-2019
Project Type : NEW
Report Online Submission Date : 29-Oct-2020
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)8757.76
2Estimated cost of construction of apartments0.00
3Estimated cost of infrastructure & other structure498.61
4Other cost including EDC taxes, levies, etc5519.19
Total14775.56



Name of the approvalStatusDate
Layout PlanObtained Approval on17-09-2019
Demarcation PlanObtained Approval on17-09-2019
Zoning PlanObtained Approval on17-09-2019
Service PlansObtained Approval on08-03-2021
Electricity PlansHave not applied till dateN/A



Name of the approvalStatusDate
Demarcation PlanObtained Approval on11-09-2019
Zoning PlanHave not applied till dateN/A
Service PlansObtained Approval on08-03-2021
Electricity PlansHave not applied till dateN/A
Site PlansObtained Approval on11-09-2019
Building PlansObtained Approval on11-09-2019
FIre NOCHave not applied till dateN/A
Total Expenditure on the project498.611
Expenditure made upto the date of Registration0



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total0



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure152.19
3Other costs including EDC, taxes, etc7.64
Total159.83
Balance5927.52



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account1056
3Amount withdrawn during the quarter1039.25
4Balance at the end of the quarter16.75
Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1OPEN PARKING0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date1345.36
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 28-10-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 28-10-2020  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 28-10-2020  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 28-10-2020  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 29-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total0



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure27.72
3Other costs including EDC, taxes, etc0
Total27.72
Balance5899.80



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter16.75
2Amount deposited in Escrow Account5.0
3Amount withdrawn during the quarter10.45
4Balance at the end of the quarter11.30
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOT0



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1OPEN PARKING0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date1454.82
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 29-10-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 29-10-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 29-10-2020  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 29-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 29-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments325.89
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total325.89



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure8.9
3Other costs including EDC, taxes, etc4.76
Total13.66
Balance5886.14



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter11.30
2Amount deposited in Escrow Account228.12
3Amount withdrawn during the quarter94.82
4Balance at the end of the quarter144.61
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOT18



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOT18



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1OPEN0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date2334.86
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 29-10-2020  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 29-10-2020  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 29-10-2020  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 29-10-2020  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 29-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance144.61
2Amount collected from allottees against booked plots and/or apartments1622.96
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates100.00
5Any other receipt0
Total1867.57



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure134.03
3Other costs including EDC, taxes, etc602.51
Total736.53
Balance1131.04



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter144.61
2Amount deposited in Escrow Account1722.96
3Amount withdrawn during the quarter1522.97
4Balance at the end of the quarter344.61
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOT21



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOT21



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure322.84
2Apartments0
3EDC, IDC, etc575.00
4Others Expenditure87.04



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date657.00
2EDC due as on date1677.86
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-01-2021  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-01-2021  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-01-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-01-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-01-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance344.61
2Amount collected from allottees against booked plots and/or apartments1924.96
3Amount availed from the bank/financial institutions0.00
4Amount contributed by the promoters/his associates0.00
5Any other receipt1889.00
Total4158.57



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0.00
2Expenditure on infrastructure & other structure132.37
3Other costs including EDC, taxes, etc24.32
Total156.69
Balance4001.88



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter344.61
2Amount deposited in Escrow Account3813.96
3Amount withdrawn during the quarter3802.97
4Balance at the end of the quarter355.60
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOT17



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOTS SOLD OUT OF TOTAL 10517



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure132.37
2Apartments0
3EDC, IDC, etc0
4Others Expenditure24.32



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date575.00
2EDC due as on date1759.86
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-04-2021  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-04-2021  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-04-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-04-2021  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-04-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance355.60
2Amount collected from allottees against booked plots and/or apartments1960.11
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt1048.14
Total3363.85



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure169.70
3Other costs including EDC, taxes, etc221.75
Total391.45
Balance2972.40



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter355.60
2Amount deposited in Escrow Account3008.26
3Amount withdrawn during the quarter3032.00
4Balance at the end of the quarter331.86
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS 17



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOTS 17



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure169.70
2Apartments0
3EDC, IDC, etc0
4Others Expenditure221.75



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date657.00
2EDC due as on date1677.86
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-07-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-07-2021  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-07-2021  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-07-2021  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-07-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance331.86
2Amount collected from allottees against booked plots and/or apartments5504.91
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt2524.24
Total8361.01



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure205.67
3Other costs including EDC, taxes, etc308.27
Total513.94
Balance7847.07



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter331.86
2Amount deposited in Escrow Account8029.14
3Amount withdrawn during the quarter5471.15
4Balance at the end of the quarter2889.85
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS 30



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOTS30



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure205.67
2Apartments0
3EDC, IDC, etc0
4Others Expenditure308.27



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date657.00
2EDC due as on date1677.86
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 13-10-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 13-10-2021  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 13-10-2021  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 13-10-2021  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 13-10-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2889.85
2Amount collected from allottees against booked plots and/or apartments2004.34
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt357.42
Total5251.61



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure249.05
3Other costs including EDC, taxes, etc1001.56
Total1250.61
Balance4001.00



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter2889.85
2Amount deposited in Escrow Account6825.93
3Amount withdrawn during the quarter6275.90
4Balance at the end of the quarter3439.88
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOT6



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure249.05
2Apartments0
3EDC, IDC, etc0
4Others Expenditure489.56



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date1169.00
2EDC due as on date3411.32
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 11-01-2022  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 11-01-2022  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 12-01-2022  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 12-01-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 12-01-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3439.88
2Amount collected from allottees against booked plots and/or apartments1003.87
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt19.74
Total4463.49



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure185.63
3Other costs including EDC, taxes, etc3548.47
Total3734.10
Balance729.39



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter3439.88
2Amount deposited in Escrow Account1023.62
3Amount withdrawn during the quarter3813.63
4Balance at the end of the quarter649.87
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS 1



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOTS1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure185.63
2Apartments0
3EDC, IDC, etc3358.20
4Others Expenditure190.27



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date3358.20
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-04-2022  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-04-2022  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-04-2022  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-04-2022  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-04-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance649.86
2Amount collected from allottees against booked plots and/or apartments18.22
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt3.77
Total671.85



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure205.44
3Other costs including EDC, taxes, etc32.56
Total238.00
Balance433.85



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter649.87
2Amount deposited in Escrow Account21.99
3Amount withdrawn during the quarter0
4Balance at the end of the quarter671.85
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS 2



Total Apartments in the colony105
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1SCO PLOTS2



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure205.44
2Apartments0
3EDC, IDC, etc0
4Others Expenditure32.56



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date4527.00
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 12-07-2022  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 12-07-2022  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 12-07-2022  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 12-07-2022  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 12-07-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance671.85
2Amount collected from allottees against booked plots and/or apartments13.18
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0.00
Total685.03



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure53.54
3Other costs including EDC, taxes, etc9.90
Total63.44
Balance621.59



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter671.85
2Amount deposited in Escrow Account13.18
3Amount withdrawn during the quarter13.18
4Balance at the end of the quarter671.85
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure53.54
2Apartments0
3EDC, IDC, etc0
4Others Expenditure9.9



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date4527.00
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 12-10-2022  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 12-10-2022  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 12-10-2022  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-10-2022  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-10-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance671.85
2Amount collected from allottees against booked plots and/or apartments0.00
3Amount availed from the bank/financial institutions0.00
4Amount contributed by the promoters/his associates0.00
5Any other receipt0.00
Total671.85



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0.00
2Expenditure on infrastructure & other structure54.74
3Other costs including EDC, taxes, etc63.07
Total117.82
Balance554.03



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter671.85
2Amount deposited in Escrow Account0.00
3Amount withdrawn during the quarter0.00
4Balance at the end of the quarter671.85
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure54.74
2Apartments0
3EDC, IDC, etc0
4Others Expenditure63.07



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date4580.34
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-01-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-01-2023  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-01-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 16-01-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 16-01-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance671.85
2Amount collected from allottees against booked plots and/or apartments138.51
3Amount availed from the bank/financial institutions0.00
4Amount contributed by the promoters/his associates0.00
5Any other receipt0.00
Total810.36



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0.00
2Expenditure on infrastructure & other structure86.26
3Other costs including EDC, taxes, etc14.84
Total101.10
Balance709.27



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter671.85
2Amount deposited in Escrow Account138.51
3Amount withdrawn during the quarter810.36
4Balance at the end of the quarter0.00
Total Plots in the colony105
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1SCO PLOTS0



Total Apartments in the colony0
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1NIL0
2TOTAL NUMBER OF PLOTS105
3SOLD IN THIS QUARTER0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure86.26
2Apartments0.00
3EDC, IDC, etc0.00
4Others Expenditure14.84



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date4580.34
2EDC due as on date0.00
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2023  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2023  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2023  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2023  View