S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)3596.84
2Estimated cost of construction of apartments8904.40
3Estimated cost of infrastructure & other structure1108.24
4Other cost including EDC taxes, levies, etc4056.38
Total17665.86



Name of the approvalStatusDate
Demarcation PlanObtained Approval on05-07-2019
Zoning PlanObtained Approval on02-08-2019
Service PlansObtained Approval on22-11-2019
Electricity PlansHave not applied till dateN/A
Site PlansObtained Approval on22-11-2019
Building PlansObtained Approval on22-11-2019
FIre NOCObtained Approval on17-05-2020
Total Expenditure on the project2257.28
Expenditure made upto the date of Registration3718.32



EDC due as on the date of Registration596.86

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates806.68
5Any other receipt0
Total806.68



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments159.42
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc647.26
Total806.68
Balance0



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments1283.45
3EDC, IDC, etc91.83
4Others Expenditure882



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date119.38
2EDC due as on date477.48
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2020  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2020  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2020  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments3123.10
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3123.10



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments525.65
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc148.43
Total674.08
Balance2449.02



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account3123.10
3Amount withdrawn during the quarter3123.10
4Balance at the end of the quarter0
Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1TYPE764



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TYPE0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments525.65
3EDC, IDC, etc0
4Others Expenditure148.43



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date119.38
2EDC due as on date477.48
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2020  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2449.20
2Amount collected from allottees against booked plots and/or apartments505.10
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates-500
5Any other receipt0
Total2454.3



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments286.10
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc122
Total408.10
Balance2046.2



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account505.10
3Amount withdrawn during the quarter505.10
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1TYPE0



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1TYPE143



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TYPE0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments286.10
3EDC, IDC, etc0
4Others Expenditure122



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date119.38
2EDC due as on date477.48
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 04-03-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 04-03-2021  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 04-03-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 04-03-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 04-03-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2046.2
2Amount collected from allottees against booked plots and/or apartments2058.90
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates-500
5Any other receipt0
Total3604.92



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments358.33
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc709.46
Total1067.79
Balance2537.13



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account2058.90
3Amount withdrawn during the quarter2058.90
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1TYPE 10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1TYPE 18



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TYPE 10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments358.33
3EDC, IDC, etc96.06
4Others Expenditure613.40



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date226.76
2EDC due as on date370.1
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 05-06-2021  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 05-06-2021  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 05-06-2021  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 05-06-2021  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 05-06-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2537.13
2Amount collected from allottees against booked plots and/or apartments489.30
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3026.43



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments691.69
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc81.20
Total772.89
Balance2253.54



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account489.30
3Amount withdrawn during the quarter489.30
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1TYPE 10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1TYPE 11



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TYPE 10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments691.69
3EDC, IDC, etc0
4Others Expenditure81.20



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date238.76
2EDC due as on date358.1
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 07-08-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 07-08-2021  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 07-08-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 07-08-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 07-08-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2253.54
2Amount collected from allottees against booked plots and/or apartments1597.40
3Amount availed from the bank/financial institutions-406.68
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total1190.72



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments788.87
2Expenditure on infrastructure & other structure160.90
3Other costs including EDC, taxes, etc0
Total949.77
Balance2494.49



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account1597.4
3Amount withdrawn during the quarter1597.4
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL & COMMERCIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments788.87
3EDC, IDC, etc0
4Others Expenditure160.90



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date249.00
2EDC due as on date156.91
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 23-11-2021  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 23-11-2021  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 23-11-2021  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 25-11-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 25-11-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2494.49
2Amount collected from allottees against booked plots and/or apartments353.50
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total2847.99



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments180.69
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc78.12
Total258.90
Balance2589.09



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter353.50
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter353.50
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments180.69
3EDC, IDC, etc14.10
4Others Expenditure64.11



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date429.16
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 26-01-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 26-01-2022  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 26-01-2022  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 26-01-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 26-01-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2589.09
2Amount collected from allottees against booked plots and/or apartments2680.60
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total5269.69



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments672.79
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc120.54
Total793.33
Balance2976.36



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account2680.60
3Amount withdrawn during the quarter2680.60
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL68



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments672.79
3EDC, IDC, etc0
4Others Expenditure120.54



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date429.16
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 29-05-2022  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 29-05-2022  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 29-05-2022  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 29-05-2022  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 29-05-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2976.36
2Amount collected from allottees against booked plots and/or apartments678.12
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total3654.48



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments506.22
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc69.58
Total575.80
Balance3078.68



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account678.12
3Amount withdrawn during the quarter678.12
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NA0



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL3



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments506.22
3EDC, IDC, etc0
4Others Expenditure69.58



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date263.03
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 13-09-2022  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 13-09-2022  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 13-09-2022  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 13-09-2022  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-09-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3078.68
2Amount collected from allottees against booked plots and/or apartments1355.76
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4434.44



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments631.52
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc217.39
Total848.91
Balance3585.53



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account1355.76
3Amount withdrawn during the quarter1355.76
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NA0



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL1



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments631.52
3EDC, IDC, etc93.19
4Others Expenditure124.20



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date93.19
2EDC due as on date356.22
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-11-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 12-11-2022  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 12-11-2022  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-11-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-11-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3678.71
2Amount collected from allottees against booked plots and/or apartments734.95
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4413.67



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments504.13
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc126.81
Total630.94
Balance3782.73



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account734.96
3Amount withdrawn during the quarter734.96
4Balance at the end of the quarter0.0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NA0



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL2



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments504.13
3EDC, IDC, etc79.85
4Others Expenditure46.96



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date79.85
2EDC due as on date436.07
Sr. No.Document DescriptionDate of Upload Document View
1 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 22-01-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 22-01-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 23-01-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 23-01-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 23-01-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3689.54
2Amount collected from allottees against booked plots and/or apartments1642.41
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total5331.95



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments644.53
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc82.72
Total727.25
Balance4604.70



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.0
2Amount deposited in Escrow Account1642.41
3Amount withdrawn during the quarter1642.41
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NA0



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL4
2COMMERCIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments644.53
3EDC, IDC, etc74.83
4Others Expenditure7.89



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date74.83
2EDC due as on date510.90
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 10-05-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 10-05-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 10-05-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 10-05-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 10-05-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance4604.70
2Amount collected from allottees against booked plots and/or apartments131.08
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4735.78



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments350.87
2Expenditure on infrastructure & other structure27.10
3Other costs including EDC, taxes, etc0.00
Total377.97
Balance4357.81



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account131.08
3Amount withdrawn during the quarter131.08
4Balance at the end of the quarter0.00
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NA0



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL0
2COMMERCIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments350.87
3EDC, IDC, etc0.00
4Others Expenditure27.10



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0.00
2EDC due as on date510.90
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 28-07-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 28-07-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 28-07-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 28-07-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 28-07-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance4357.81
2Amount collected from allottees against booked plots and/or apartments1878.85
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total6236.66



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments519.85
2Expenditure on infrastructure & other structure0.00
3Other costs including EDC, taxes, etc24.11
Total543.96
Balance5692.71



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account1878.85
3Amount withdrawn during the quarter1878.85
4Balance at the end of the quarter0.00
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL0
2COMMERCIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0.00
2Apartments519.85
3EDC, IDC, etc0.00
4Others Expenditure24.11



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0.00
2EDC due as on date510.90
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 27-10-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 27-10-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 27-10-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 27-10-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 27-10-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance5692.71
2Amount collected from allottees against booked plots and/or apartments24.62
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total5717.33



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments234.70
2Expenditure on infrastructure & other structure0.00
3Other costs including EDC, taxes, etc106.60
Total341.30
Balance5376.03



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account24.62
3Amount withdrawn during the quarter24.62
4Balance at the end of the quarter0.00
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony780
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL0
2COMMERCIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0.00
2Apartments234.70
3EDC, IDC, etc0.00
4Others Expenditure106.60



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0.00
2EDC due as on date510.90
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 25-01-2024  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 25-01-2024  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 25-01-2024  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 25-01-2024  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 25-01-2024  View