HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-570-2019
Submission Date : 28-06-2019 03:06:06 AM
Applicant Type : Company
Project Type: ONGOING




ARIHANT INFRRA REALTORS PVT. LTD.
OFFICE NO. 601, PLOT NO.17, SACHDEVA TOWER, COMMUNITY CENTRE, KARKARDOOMA, DELHI-110092
01145681580
9582261535 (Number Shared by Promoter in Public)
nipun.jain@arihantgroup.co.in
http://arihantbuildcon.com
XXXX625N
U70102DL2010PTC201417
 
 


 
 


 
 


 
 







ARIHANT SOUTH WINDS
GH 01 SECTOR 41 SURAJKUND
FARIDABAD
FARIDABAD
9582261535
9582261535 (Number Shared by Promoter in Public)
info.airpl@arihantgroup.co.in
NIPUN JAIN
01145681580
9582261535 (Number Shared by Promoter in Public)
nipun.jain@arihantgroup.co.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150007250007131-07-2017287305ICICI BANK LTDHRERA Panchkula







1.62 (Acre)
175
174
1.62 (Acre)
MCF/JC (F)/2013/1388
Yes







11500 Lakhs
5845 Lakhs
3775 Lakhs
587 Lakhs
1293 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1608.951
3CONSTRUCTION OF ROADS1838.756
4PAVEMENTS500
5PARKS AND PLAYGROUNDS1298.18
6GREEN BELTS0
7VEHICLE PARKINGS75
8ELECTRICITY SUB-STATION9
9CLUB HOUSE165.5
10SEWAGE AND SOLID WASTE TREATMENT FACILITY27
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER1044.573
Total6566.96




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSMUNICIPAL CORPORATION FARIDABADNo
WATER SUPPLYMUNICIPAL CORPORATION FARIDABADNo
ELECTRICITYMUNICIPAL CORPORATION FARIDABADNo
SEWAGE DISPOSALMUNICIPAL CORPORATION FARIDABADNo
STORM WATER DRAINAGEMUNICIPAL CORPORATION FARIDABADNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS50AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM40AS PER PROJECT REPORT
3STORM WATER DRAINAGE10AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM100AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL22AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING15AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS15AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE75AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER260AS PER PROJECT REPORT


25-10-2013 (date)
25-10-2013 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK116.849220220
2APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK+SERVANT136.848241231
3APARTMENT/SHOPS/OTHER BUILDINGS Type 4BHK+SERVANT170.779240240






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
4BHK+SERVANT1STRUCTURE WORK COMPLETED AND FINISHING WORK IS IN PROCESS


01-08-2015
31-12-2020
31-12-2020
01-01-2019
20
31-12-2020
PROVIDED
REQUIRED MANPOWER AND MATERIAL HAS BEEN MADE AVAILABLE AT SITE


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-01-2019
20
31-12-2020
PROVIDED
REQUIRED MANPOWER AND MATERIAL HAS BEEN MADE AVAILABLE AT SITE


119
0
33
6
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments2553.49
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments200200200
Shops000
Plots000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments20020020021.51
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements10.14
Water Supply System0
Sewerage treatment & garbage disposal4.09
Electricity Supply System0
Storm Water Drainage4.32
Parks and Playgrounds0
Clubhouse/community centres29.64
Shopping area0
Other127.46

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements555
Water Supply System0020
Sewerage treatment & garbage disposal222
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres335
Shopping area000
Other151515

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements57.57.54.86
Water Supply System20000
Sewerage treatment & garbage disposal233.53.41
Electricity Supply System3030400
Storm Water Drainage1220.68
Parks and Playgrounds007.57.5
Clubhouse/community centres512125.36
Shopping area0000
Other20253027.54












Particulars Remarks, if any
i. No. of Flats/Apartments constructed70
ii. No. of Flats/ Apartments booked1
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter174.52 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter28.98 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter145.54 Lakhs
vii. Amount invested in the project upto the date of application6704.18 Lakhs
Land cost (If any)2768.59 Lakhs
Apartments2553.49 Lakhs
Infrastructure175.65 Lakhs
EDC/ Taxes Etc.1206.45 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession4795.82 Lakhs
(a) In respect of existing allottees45 Lakhs
(b) In respect of rest of the project4750.82 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
3250 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 4583.49 LakhsIncluding amount payable to MCF



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS5010.14
II. WATER SUPPLY SYSTEM400
III. STORM WATER DRAINAGE104.32
IV. ELECTRICITY SUPPLY SYSTEM1000
V. SEWAGE TREATMENT & GARBAGE DISPOSAL154.09
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM70
X. CLUBHOUSE7529.64
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.150
XIII. COVERED PARKING250127.46
XIV. OPEN PARKING100
XV. GARAGES00
XVI. SECURITY SYSTEM150
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
HDFC BANK LTD 122 HARGOBIND ENCLAVE NEW DELHI 110092
57500000040434
HDFC0000481
110240073
0481
Mr Kaushal Kumar Jain 149 Vigyan Vihar Delhi Mr Rajiv Jain 149 Vigyan Vihar Delhi Mr Rajesh Jain C 181 Anand Vihar Delhi
No Default











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. HEIGHT NOCALREADY BEEN OBTAINED13-01-2014
II. FIR NOCALREADY BEEN OBTAINED03-01-2014
III. FOREST NOCALREADY BEEN OBTAINED03-01-2014
IV. POLLUTION NOCALREADY BEEN OBTAINED19-08-2014
V. PERMISSION OF RAINWATER HARVESTINGALREADY BEEN OBTAINED04-04-2019








No


Yes


Details of parties, Property description, sale consideration, events of default, date of possession, defect liability clause













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEMARBLE FLOORING IN DRAWING ROOM & KITCHEN, TILES FLOORING IN ALL ROOMS
2WALL FINISHING DETAILSPLASTIC EMULSION PAINT WITH DECORATIVE WALL PAPER (AS PER SPECIFICATION SHEET)
3KITCHEN DETAILSMARBLE FLOORING WITH 2FT TILES ABOVE THE GRANITE KITCHEN SLAB, R.O AND S.S SINK
4BATHROOM FITTINGSGROHE CP FITTING & AMERICAN STANDARD WC, IMPORTED VANITY WITH BASIN.
5WOOD WORK ETCMODULAR KITCHEN & CUPBOARDS (OPTIONAL)
6DOORS AND WINDOS FRAMESDOOR 8FT HEIGHT CHOKHAT OF CHAAPWOOD WITH FLUSH DOOR WITH POLISH & VINEER, WINDOW UPVC
7GLASS WORKS S RAILING WITH SAFTEY GLASS
8ELECTRIC FITTINGSFROM REPUTED BRANDS
9CONDUCTING AND WIRING DETAILSAS PER DRAWING
10CUPBOARD DETAILSFULL MODULAR CUP BOARDS
11WATER STORAGEADEQUATE CAPACITY OF UNDER GROUND & OVERHEAD TANK
12LIFT DETAILSSCHINEIDER MAKE
13EXTERNAL GLAZINGSENTRANCE LOBBY OF EACH TOWER WITH GLASS
13.1WINDOWS/GLAZINGSUPVC WITH GLASS
14DOORSFLUSH DOOR WITH VINNER & POLISH
14.1MAIN DOORSFLUSH DOOR WITH VINNER & POLISH
14.2INTERNAL DOORSFLUSH DOOR WITH VINNER & POLISH
15AIR CONDITIONINGSTANDARD SPLIT AC (OPTIONAL)
16ELECTRICAL FITTINGSAS PER MEP CONSULTANT
17CNG PIPE LINEGAS PIPE LINE IN KITCHEN (AS PER IGL TERM & CONDITION)
18PROVISION OF WIFI AND BROADBAND FACILITYINSIDE APARTMENT
19EXTERNAL FINISHING/COLOUR SCHEMEULTIMA PAINT OF ASIAN
20INTERNAL FINISHINGPLASTIC PAINT (INSIDE OF FLAT)
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORIMPORTED MARBLES
1 . 2 WALLSONE DRAWING ROOM WALL WITH DECORATIVE WALL PAPER REST WALLS WITH PLASTIC EMULSION PAINT.
1 . 3 CEILINGDESIGNER POP FALSE CEILING IN DRAWING ROOM
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORTILES
2 . 2 WALLSONE ROOM WALL WITH DECORATIVE WALL PAPER REST WALLS WITH PLASTIC EMULSION PAINT.
2 . 3 CEILINGDESIGNER POP FALSE CEILING.
2 . 4 MODULAR WARDROBESFACTORY MANUFACTURED PRE-ASSEMBLED WARDROBES.
3 . MASTER TOILET
3 . 1 FLOORTILES
3 . 2 WALLSTILES
3 . 3 CEILINGFALSE CEILING WITH PLASTIC PAINT
3 . 4 COUNTERSIMPORTED DOUBLE SINK WITH VANITY
3 . 5 SANITARY WARE/CP FITTINGSTOP OF THE LINE GROHE/AMERICAN STANDARD
3 . 6 FITTING/FIXTURESTOP OF THE LINE GROHE/AMERICAN STANDARD
4 . BED ROOMS
4 . 1 FLOORTILES
4 . 2 WALLSONE ROOM WALL WITH DECORATIVE WALL PAPER REST WALLS WITH PLASTIC EMULSION PAINT.
4 . 3 CEILINGDESIGNER POP FALSE CEILING IN ROOM
4 . 4 WARDROBESFACTORY MANUFACTURED PRE-ASSEMBLED WARDROBES.
5 . TOILET
5 . 1 FLOORTILES
5 . 2 WALLSDESIGNER TILES (UP TO CEILING)
5 . 3 CEILINGPLASTIC EMULSION PAINT
5 . 4 COUNTERSIMPORTED SINGLE BASIN
5 . 5 SANITARY WARE/CP FITTINGSTOP OF THE LINE GROHE/AMERICAN STANDARD./IMPORTED VANITY AND BASIN (OPTIONAL)
5 . 6 FIXTURESTOP OF THE LINE GROHE/AMERICAN STANDARD.
6 . KITCHEN
6 . 1 FLOORIMPORTED MARBLES
6 . 2 WALLSTILES ABOVE THE GRANITE KITCHEN SLAB (ABOVE 2FT.)
6 . 3 CEILINGDESIGNER POP FALSE CEILING
6 . 4 COUNTERSGRANITE WORKING COUNTER
6 . 5 FIXTURESFACTORY MANUFACTURED MODULAR KITCHEN
6 . 6 KITCHEN APPLIANCESDESIGNER MODULAR KITCHEN HAVING SS SINK AND R.O., PROVISION OF PIPE GAS SUPPLY.(AS PER IGL)
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES
7 . 2 WALLS & CEILINGTRACTOR EMULSION PAINT
7 . 3 TOILETTILES FLOORING WITH TRACTOR EMULSION PAINT ON WALLS
7 . 4 BALCONYS S RAILING WITH SAFETY GLASS
8 . SIT-OUTS
8 . 1 FLOORTREE MIX OR PAVERS
8 . 2 WALLS & CEILINGTILES/GRANITE CLADING
8 . 3 RAILINGSS S OR M S RALLINGS (AS PER DRAWINGS)
8 . 4 FIXTURESWATER BODY WITH STONE STACHUE OUTER AREA












Sr. No.Document DescriptionDate of Document UploadView Document
1NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT24-06-2019 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND24-06-2019 View Document
3SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN24-06-2019 View Document
4DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD24-06-2019 View Document
5IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN24-06-2019 View Document
6DEMARCATION PLAN24-06-2019 View Document
7ZONING PLAN24-06-2019 View Document
8IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN24-06-2019 View Document
9A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS24-06-2019 View Document
10CASH FLOW STATEMENT OF THE PROPOSED PROJECT24-06-2019 View Document
11CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT24-06-2019 View Document
12DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.25-06-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 CERTIFICATE FOR EXTENSTION OF REGISTRATION 25-06-2021 View Document
2 CERTIFICATE OF SECOND EXTENSION 02-09-2022 View Document