Quarterly Schedules

HRERA Panchkula
Project Registration Number : 29/2017, DATED 02.08.2017
Project Name : GROUP HOUSING PROJECT "SANSARA RESIDENCIES"
Project Number : RERA-PKL-621-2019
Project Type : ONGOING
Report Online Submission Date : 08-Jul-2020



ParticularsExpenditure already incurred up to the date of registration.
(In Lakhs)
Total Estimated/ Revised cost of project. (In Lakhs)
Land18061866
Building20987534
Infrastructure facilities, etc.06151
Other costs including EDC, IDC, etc.18662648
Total577010380



Name of the approvalStatusDate
Layout PlanHave not applied till dateN/A
Demarcation PlanHave not applied till dateN/A
Zoning PlanHave not applied till dateN/A
Service PlansHave not applied till dateN/A
Electricity PlansHave not applied till dateN/A



Name of the approvalStatusDate
Demarcation PlanHave not applied till dateN/A
Zoning PlanObtained Approval on15-04-2011
Service PlansOn expiry have not applied till dateN/A
Electricity PlansOn expiry have not applied till dateN/A
Site PlansObtained Approval on19-08-2011
Building PlansObtained Approval on19-08-2011
FIre NOCHave not applied till dateN/A
Total Expenditure on the project6151
Expenditure made upto the date of Registration0



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0.908
2Amount collected from allottees against booked plots and/or apartments3865
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates1291
5Any other receipt0
Total5156



S.No.Cash OutflowAmount
(In Lakhs)
1Land1524
2Cost of construction of apartments2056
3Cost of infrastructure & other structure0
4Other costs including EDC, taxes, etc1576
Total5156
Balance5224



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.908
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0.02419
4Balance at the end of the quarter0.884
Total Apartments in the colony144
Apartments sold upto the date of Registration65



S.No.Type/SizeApartments Sold in the Quarter
1TYPE 1 (3BHK WITH SERVANT ROOM & LAWN)0
2TYPE 2 (3BHK WITH TERRACE)0
3TYPE 3 (2BHK TYPE-1)0
4TYPE 4 (2BHK TYPE-2)0
5TYPE 2 (3BHK WITH TERRACE)0
6TYPE 3 (2BHK TYPE-1)0
7TYPE 4 (2BHK TYPE-2)0



Total Garages in the colony0
Garages sold upto the date of Registration65



S.No.Type/SizeGarages Sold in the Quarter
1PARKING0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments5702
3EDC, IDC, etc726
4Others Expenditure850



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date726
2EDC due as on date1938
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 08-07-2020  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 08-07-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 08-07-2020  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 08-07-2020  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 08-07-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0.908
2Amount collected from allottees against booked plots and/or apartments3865
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates1291
5Any other receipt0
Total5156



S.No.Cash OutflowAmount
(In Lakhs)
1Land1524
2Cost of construction of apartments2056
3Cost of infrastructure & other structure0
4Other costs including EDC, taxes, etc1576
Total5156
Balance5224



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.908
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0.0241
4Balance at the end of the quarter0.884
Total Plots in the colony144
Plots sold upto the date of Registration65



S.No.Type/SizePlots Sold in the Quarter
1TYPE 1 (3BHK WITH SERVANT ROOM & LAWN)0
2TYPE 2 (3BHK WITH TERRACE)0
3TYPE 3 (2BHK TYPE-1)0
4TYPE 4 (2BHK TYPE-2)0



Total Apartments in the colony144
Apartments sold upto the date of Registration65



S.No.Type/SizeApartments Sold in the Quarter
1ALL TYPES AS ABOVE0



Total Garages in the colony0
Garages sold upto the date of Registration65



S.No.Type/SizeGarages Sold in the Quarter
1PARKING0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments5702
3EDC, IDC, etc726
4Others Expenditure850



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date726
2EDC due as on date1938
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 08-07-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 08-07-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 08-07-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 08-07-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 08-07-2020  View